| Job | Price | With ROT |
|---|---|---|
Pool, electrical connection – pump and heat pump IP65 distribution board, cabling and local isolator switch. | SEK 10,302 | SEK 9,270 |
Hot tub, electrical connection Local isolator switch and RCD. | SEK 6,966 | SEK 6,028 |
Electrical connection of pump, incl. junction box Cable and new junction box. | SEK 4,622 | SEK 4,106 |
Electrical connection of pump, excl. junction box Connection in the existing box. | SEK 3,070 | SEK 2,683 |
All prices are in Swedish kronor (SEK) including 25 per cent VAT, materials and installation. A travel charge of SEK 500 is added. The price with ROT is the price after the deduction, if you are a private individual and are entitled to it.
What does the electrical connection of a pool or a hot tub cost?
The electrical connection of a hot tub costs SEK 6,966. The electrical connection of a pool with pump and heat pump costs SEK 10,302. Materials, installation and VAT are included in both, and a travel charge of SEK 500 is added.
The amounts cover the electrical work itself. You buy the hot tub, the pool pump and the heat pump separately.
Which line applies to you?
| You have | Line in the price list | This is included |
|---|---|---|
| A hot tub that is to be permanently connected | Hot tub, electrical connection | Local isolator switch and residual current device (RCD) |
| A pool with pump and heat pump | Pool, electrical connection | IP65 distribution board, cabling and local isolator switch |
| A pump where there is already a box to connect it in | Pump excluding junction box | Connection in the existing box |
| A pump where there is no box | Pump including junction box | Cable and new junction box |
A few words used in the lines:
- A local isolator switch sits by the equipment and makes it dead when it is to be serviced.
- An RCD cuts the power when current leaks to earth.
- IP65 is the enclosure’s protection against dust and water. The second digit, 5, means that the enclosure withstands water jets.
The pump lines apply to a pump that is to be permanently connected. Connection in an existing box costs SEK 3,070. If the pump has a plug, you may plug it into an earthed socket yourself.
What the price assumes
The lines state no cable length. The distance between the consumer unit and the pool or the hot tub is what most often decides whether the job is a standard installation. Send these details with your enquiry:
- the distance from the consumer unit to the site, and how the cable can be run
- the power of the equipment and whether it needs single-phase or three-phase, according to the rating plate or the manual
- the size of the house’s main fuse, that is, the fuses where the electricity comes into the house
- a photo of the consumer unit, so that we can see whether there is room for a new circuit
A hot tub can draw so much electricity that the main fuse has to be raised. That is a separate line in the price list for meter cabinet and main fuse. Raising from 25 A to 35 A costs SEK 4,250 with pre-notification and completion notice (för- och färdiganmälan), provided the service cable is sized for it. The notices are filed before and after the work with the grid operator (elnätsföretag), the company that owns the local grid, not the company you buy electricity from, and the service cable is the cable from the grid to the meter cabinet. How you know whether the fuse is large enough is in the article on raising the main fuse.
Cable in the ground and notification to the grid operator
The price assumes that there is a cable route. If the cable is to be buried, the trench is not included in the price. You can dig it yourself or have a groundworks contractor do it. The cable and the conduit, on the other hand, must be laid by the electrical installation company (elinstallationsföretag). This follows from the answer on cable in the ground from the Swedish National Electrical Safety Board, Elsäkerhetsverket. Check in Ledningskollen where existing cables and pipes lie before anyone digs.
Whether a hot tub needs a pre-notification depends on the grid operator. Kraftringen Nät states that at present it does not require pre-notification for hot tubs. With other grid operators we check what applies. If the main fuse is to be changed, a notification is always filed.
We are based in Malmö and work in Malmö and the rest of Skåne. More electrical jobs that belong to the plot and the house are on the page for detached and terraced houses.
ROT for pool and hot tub
The price list shows a price with the Swedish ROT tax deduction for labour on your home (ROT-avdrag) for each line, for example SEK 6,028 for the hot tub. The conditions can vary. The Swedish Tax Agency, Skatteverket, gives the ROT deduction for electrical work in the home or on the plot close to the home, but not for running power in the garden. The deduction is only given on the labour cost and only to private individuals who own their home. Ask us before you count on the lower price.
What applies to the prices
- A standard installation in a place that is accessible
- The existing cable route can be used
- The prices apply to standard installations under the conditions above.
- Extra work may be added if the existing electrical installation has faults.
- Fault-finding in the existing electrical installation is included only where this is expressly stated.
- Prices are shown including 25 per cent VAT.
- A travel charge of SEK 500 is added. Charges for driving to the site or setting up on site may be added.
- The ROT deduction (the Swedish tax deduction for labour on your home) applies to private individuals and work in the home. The conditions vary, so ask us if you are unsure.
How the work is done is described on the page about controls and automation.